To view the Project Quantity Progress Details report, perform any of the following actions.
-
View the report in the Earned Value screen:
-
Navigate to Progress > Earned Value.
-
Click the Reports tab.
-
Click the Project Quantity Progress Details tab.
-
Click the Project ellipsis and select the required project. By default, the last selected project appears.
-
Click the Run icon. The Project Quantity Progress Details report appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Earned Value > Project Quantity Progress Details.
-
Click the Project ellipsis and select the required project. By default, the last selected project appears.
-
Click the Run icon. The Project Quantity Progress Details report appears.
-