This procedure allows you to update the general project structure attributes only if the Cost Control Level for the project structure is assigned.
If the Cost Control Level for a selected project structure is blank, then the project structure attributes can only be viewed but not modified.
-
In the Project Structure Details panel, expand General Information section.
-
Edit the Object ID, if required.
-
Edit the Object Name, if required.
-
(Optional) Type the number of Balance Periods.
-
(Optional) Type the number of Adjustment Periods.
-
(Optional) Type the Objective.
-
Click the ellipsis for each of the below attributes and select the required values:
-
(Optional) Contingency Account Type - Select the contingency account type
Contingency Account Type is editable only for Contingency line item type.
-
(Optional) Responsible Manager - Select the responsible manager
-
Progress Method - Select the progress method
Progress Method is editable only for Non-contingency line item type.
-
Forecast Method - Select the forecast method
Forecast Method is editable only for Non-contingency line item type.
-
(Optional) OBS Name - Select the OBS name
-
(Optional) CBS Name - Select the CBS name
-
(Optional) ABS Name - Select the ABS name
-
(Optional) Forecast Balance Method - Select the forecast balance method
-
(Optional) Forecast Adjustment Method - Select the forecast adjustment method
-
(Optional) ICMS Cost Categories and Groups - Select the ICMS cost categories and groups
-
-
Click SAVE.