You can view the tasks and cost object in a combined hierarchy. Combined view is available for Scheduler charts where subject area is Task. To view the tasks and cost object in a hierarchy, Tasks must be created for the cost objects.
To enable the Hierarchy mode, navigate to the Charts > Chart Elements tab and select Enable check box.
When you save the changes, the chart is refreshed and the cost object and tasks appear as Tasks > Owner Cost Object > Cost Object Tree
The Start and End Date fields roll-up from the Task to the Owner Cost Object and then to the Cost Object Hierarchy.
-
If the Cost Object has no tasks, it will not appear in the hierarchy.
-
Early/Late dates do not roll-up
-
Task rows are editable and support row events
-
Cost Object rows are read only and do not support row events
-
Cost Object row bars are grey thin bars showing the schedule span under them