Configure the Screen Layout with the scheduler and the progress form - EcoSys - 9.1 - Administration & Configuration - Hexagon

EcoSys Scheduler

Language
English
Product
EcoSys
Search by Category
Administration & Configuration
EcoSys Version
9.1

You can define the screen layout to run the scheduler automatically once you save the progress of the data. Define a row event from the scheduler chart to load the progress form and also specify the option event to run the scheduler on the scheduler chart upon saving on the form. Scheduler chart and progress form need to be in the same Screen Layout(cannot be nested)

  1. Navigate to Configure > Screen Layouts to create a new screen layout

  2. Enter the Name, Caption, and required panel from the Geometry.

  3. Click the Panels tab, and click Add New Panel +

    1. Select the Region

    2. Select the Type as Chart

    3. In the Chart field, browse for the required chart.

  4. Click Add New Panel + again

    1. Select the Region

    2. Select the Type as Form

    3. In the Form field, browse for the required Form.

  5. Click the Events tab and configure the following:

    1. In the Source Panel, select the scheduler chart.

    2. In the Source Key, select the required event such as After Schedule, After Baseline, After load.

      • After Schedule – Scheduler runs after clicking the Charts Schedule button

      • After Baseline – Scheduler runs after clicking the Charts Baseline button

    3. Select the Target Panel

    4. In the Options list, select Run Scheduler after save

  6. Click SAVE.