Creation of a CU estimate (as-built type) - HxGN EAM - 11.07.01 - Feature Briefs - Hexagon

HxGN EAM Compatible Units

Language
English
Product
HxGN EAM
Search by Category
Feature Briefs
HxGN EAM Version
11.7.1

When the work order for the project was executed, the tradesmen performing the work identified that two additional parts (i.e. 1 bracket, & 1 length of wire were required; as well as labor (Install; Electrical - 0.5 hours for each of these additional parts) to complete the work. Additionally, 5 hours of site cleanup were performed, by a general laborer trade crew with a CU standard rate of $100.00/hour. The details documenting the additional labor/parts are described in CU_LIB-02, CU_LIB-03 and CU_LIB-03 previously in the Compatible Units Library records section.

The updated work order would appear as follows:

Records updated

Quantity updated

Number of WO Activities:

One (1)

Plan Labor:

2 records:

Electrical trade, 7 hours.

(2.5 for pole + .5 for crossarms + 3 for transformer + 0.5 for bracket + 0.5 for wire)

General laborer crew trade, 5 hours

Parts:

5 records:

Pole, quantity 1.

Crossarms, quantity 2.

Transformer, quantity 1.

Bracket, quantity 1.

Wire, quantity 1.

Plan Tools:

1 record - Excavator, 3.5 hours.

Materials List:

One (1) material list generated - as per Parts records.

A CU estimate of type as As-Built can then be prepared by the estimator to reflect the updated cost details within the project:

Records updated

Quantity updated

Labor costs:

7 hours (2.5 for pole + .5 for crossarms + 3 for transformer + 0.5 for bracket + 0.5 for wire) at $40.00/hour

= $280.00

5 hours (cleanup crew) at $100.00/hour

= $500

Total Labor Costs = $780

Parts costs:

Cost of 1 pole + Cost of 2 crossarm + Cost of 1 transformer + Cost of 1 bracket + Cost of 1 wire

= $500.00 + (2 * $200.00) + $1000 + $100 + $100

= $500.00 + $400.00 + $1000 + $100 + $100

= $2100

Tools costs:

1.5 hours * $100.00/hr.

= $150.00

Services costs:

n/a

Total CU Estimate Cost:

Labor costs + Parts costs + Tools costs + Services costs

= $780 + $2100 + $150 + $0

= $3030

Finally, the As-Built CU estimate may then also be approved, indicating that all cost details associated to the estimate are now finalized.