Start the maintenance pattern for selected equipment, which will generate the first work order for all selected equipment.

To activate maintenance patterns for equipment:

  1. Select Work > WO Planning > Maintenance Patterns.

  2. Select the maintenance pattern to activate for equipment, and then click the Equipment tab.

  3. Click Activate MP.

  4. Specify this information:

    Initial Sequence - Specify the sequence number that the pattern will use to create the first maintenance pattern work order.

    A maintenance pattern does not to necessarily start with the first sequence in the list of Sequences on the Sequence tab.

    Due Date - Specify the due date of the initial work order.

    Meter #1 Due - Specify the reading due value for the first meter. The system automatically populates Meter #1 UOM.

    Meter #2 Due - Specify the reading due value for the second meter. The system automatically populates Meter #2 UOM.

  5. Select one or more equipment records, and then click Submit.