Release work orders for equipment. The system displays PM work orders that are awaiting execution and all work orders that have a status of released. You can specify which work orders should be released by specifying the WO Status of the work orders.

To release open work orders:

  1. Select one of these options:

    • Equipment > Assets

    • Equipment > Positions

    • Equipment > Systems

    • Equipment > Locations

  2. Select the equipment for which to release work orders, and then click the Open Work Orders tab.

  3. Select one or more work orders to release.

  4. Specify this information:

    WO Status - Specify Released to release the selected work orders.

    New Scheduled Start Date - Optionally, specify a new scheduled start date for the selected work orders.

  5. Click Update WOs.