SG-4615 CLONE - Work Orders - Req Start Date populated with 1 month + 1 instead of tomorrow - HxGN EAM - 12.0.1 - Release Bulletin - Hexagon

HxGN EAM Resolved Issues for 12.0.1

Language
English
Product
HxGN EAM
Search by Category
Release Bulletin
HxGN EAM Version
12.0.1

 Description 

# Standard WOs - Create a standard work order with type Parent Standard WO

# Create a standard work orders with type Standard WO. On Activites tab include a task with checklist items

# Go to children tab of parent standard wo and add the standard wo from step 2

# Work Orders - Create a new WO with standard WO from step 1. This creates a child WO.

# Select the Child WO created and click the Checklist tab

# Check the Follow Up check box on an item and Generate Follow-up WOs

# Select the Follow-up WO created from step 6 and populate the Parent WO field with the WO manually created in step 4 (not the child WO EAM creates).

# Complete Follow up WO.

*Actual Results:*

Req Start Date of child WO (WO created by EAM in step 4) is populated with next month + 1

*Expected Results:*

Req Start Date of child WO (WO created by EAM in step 4) to be populated with tomorrow

Comment: The expected result is that the child WO that was created in step 4 (the one with a sequence and step filled in) is NOT affected by the completion of the manually added child follow-up WO, since the latter does not have sequence and step filled in. So the Req Start Date of the child WO will remain blank.