 Description 

The work order status A UDF fields are populated (like shown in the steps to reproduce). The example is done with three UDFs. These values come from the PM schedules screen - equipment tab.

The question is about the change of UDF values via the PM schedules record view. When only one value is changed for thus one UDF, all the other values from the other UDFs get cleared on the work order status A record.

Why is not only the changed value from that one UDF cascaded to the work order status A record ?

*Actual results*

All UDFs are cascaded to Work Order status A when one UDF is changed

*Expected results*

Only the changed UDF is cascaded to the Work Order status A record

*Steps to reproduce*

# Create a PM fixed type

# Populate User Defined Field 03 with PM 1 (not UDF04 and UDF06)

# Add activity

# Add an equipment

# Check field : Copy UDFs to WO (might need screendesigner to make it visible)

# Fillout User Defined Fields 03, 04 and 06 with TREE1

# The work order on status A will show UDF03, UDF04, UDF06 with value TREE1

# Go back to the record view and change UDF03 to TOTO 1.

# UDF03 and UDF04 and UDF06 from A status work order will change. It should alter only UDF03.