The following table provides the process steps used by the Incoming Submittal workflow:
Process step name |
Description |
Arguments |
---|---|---|
SDVJobConversionStep |
Converts a HxGN SDx object to a Data Validator job object. |
None |
SDVUnzipStep |
Reads all the file references in an MDR submittal and unzips any zipped files that are not referenced. |
None |
SDVSplitCSVFileStep |
Splits input CSV file using properties defined in the SDV Job Details dialog box. |
None |
Import step |
Runs the import of the supplied data to the staging area database using a defined job definition. |
None |
Validate step |
Runs the validation rules on the imported data and generates a validation report. If there are validation errors, the validation report must be approved before the workflow can continue. |
Arg1: VTLValidationReportFile |
Export step |
Transfers the data to the target system and loads the data to the database. This step starts automatically if there are no validation errors. |
None |
SDVMDRProcessStep |
Creates relationships between the MDR Document Master and other document masters in the submittal using the FDWMDRDocMasters relationship definition. |
Arg1: SDA document type Arg2: FDWMDRDocMasters relationship definition between the MDR document master and other document masters. |
SDVAttachWorkflowStep |
Attaches a workflow to the HxGN SDx object. |
Arg1: EDG_SubmittalToRevision - edge definition between the objects in the workflow and the target objects. Arg2: WD_SCLBQAReviewVerification - the name of the workflow. |
SetSubmittalStateToCOMPLETED |
Sets the issue status to completed on the submittal. |
Arg1: ISPFTransmittal - Interface definition name. Arg2: SPFXmtlIssueState Arg3: e1XmtlIssueStateCOMPLETED |
Submit For Import |
Submits the submittal for import process. |
|
Validation Error Check |
Checks for any errors during the validation process. |
If a submittal contains a deliverable for an issue purpose that is not related to the current plant or the current project, the validation rules do not allow the submittal to process further, and an error is logged in the validation report. The system checks the issue purpose relationship with the parent configuration and processes the submittal accordingly.