Before proceeding, edit the calendar and mark February 26, 2022 as a holiday. To learn how to edit a calendar, refer the Create a calendar lab.
-
On the hamburger menu, click Schedule Management > Production Planning .
-
Enter the following details:
-
Time Range - 1 Week
-
View Format - Work Package Only
-
Current view period - March 7, 2022 – March 13, 2022
-
-
Click Edit at the top right corner, and navigate to the 1.3.1- Level B1 North Columns work package.
-
On the work package, click Options .
-
Select Manage Dependencies and then click Add in the Successors section.
-
Fill the details as shown in the graphic below:
-
Click SAVE.
The application has created dependencies between the 1.3.1- Level B1 North Columns and Level 1 North Beams work packages.
-
Click Option next to the Edit icon and select Show Legend.