Map cost items with schedule items - HxGN Smart Build - 4.0 U10 (4.0.10) - Training

HxGN Smart Build Controls Training

Language
English
Product
HxGN Smart Build
Subproduct
Controls
Search by Category
Training

Before proceeding, make sure you have the required schedule in your Smart Build Insight project, and budget is published from EcoSys to Smart Build Insight.

  1. In Smart Build Insight, from the hamburger menu, click Smart Mapping > 5D Mapping.

  2. In the RULE DEFINITION tab, select Cost-Schedule from the Mapping Type list.

  3. Click ADD.

  4. Enter the details as shown in the graphic below:

  5. Click SAVE to create the rule set.

  6. Enter the following details for Rule 1 > Condition 1 as shown in the graphic below:

    SHARED Tip In 5D Mapping, when you create a condition and if the Select Operator is Equal, then the application automatically displays the suitable values in Type Value box.

  7. On Rule 1, click Options and select Add Condition.

  8. Enter the following details for Rule 1 > Condition 2 as shown in the graphic below:

  9. Similarly, for Condition 2 enter following details and then click SAVE.

  10. Click ANALYSE next to Rule 1 and then navigate to the REVIEW tab.

  11. Click the Sort By option and sort the mapping suggestions in ascending or descending order based on their ID.

  12. Expand the mapping suggestions, review them.

  13. After reviewing, select the mapping suggestion and click APPROVE.

  14. Click FINISH.

    You've successfully mapped the cost items with schedule items based on Rule 1 conditions.