Before proceeding, make sure you have the required schedule in your Smart Build Insight project, and budget is published from EcoSys to Smart Build Insight.
-
In Smart Build Insight, from the hamburger menu, click Smart Mapping > 5D Mapping.
-
In the RULE DEFINITION tab, select Cost-Schedule from the Mapping Type list.
-
Click ADD.
-
Enter the details as shown in the graphic below:
-
Click SAVE to create the rule set.
-
Enter the following details for Rule 1 > Condition 1 as shown in the graphic below:
In 5D Mapping, when you create a condition and if the Select Operator is Equal, then the application automatically displays the suitable values in Type Value box.
-
On Rule 1, click Options and select Add Condition.
-
Enter the following details for Rule 1 > Condition 2 as shown in the graphic below:
-
Similarly, for Condition 2 enter following details and then click SAVE.
-
Click ANALYSE next to Rule 1 and then navigate to the REVIEW tab.
-
Click the Sort By option and sort the mapping suggestions in ascending or descending order based on their ID.
-
Expand the mapping suggestions, review them.
-
After reviewing, select the mapping suggestion and click APPROVE.
-
Click FINISH.
You've successfully mapped the cost items with schedule items based on Rule 1 conditions.