From the hamburger menu, select Administrator settings.
-
On the Administrator Settings page, select Data Import/Export.
-
Go to IMPORT tab and select Structure data from the Select Import Definition drop-down.
-
Select your project from the Select Project drop-down.
-
Click Choose File and browse Classification Structures.xlsx file on your computer and then click IMPORT.
Once the data is imported, you will receive a successful notification.
-
Click Notifications on header bar to check the notifications.
Now the classification structures Level and Code are imported.
-
Retrieve the schedule from P6 and approve the latest schedule.
As the P6 schedule has activity codes associated, work packages will be populated under respective classes of classification structures.