On the navigation bar, click Projects > Project Structure.
-
Delete the default Cost Control Item from the project structure.
-
From the Project field, select Training Project and click OK.
-
Go to Import tab, click Sheet and select Export to Excel.
-
Open the automatically downloaded excel file and create the project structure in it.
You can use the Sample Project Structure.xlsx as reference while creating this project structure.
-
After the project structure is ready, save the file. In Smart Build Controls, make sure you are in Project Structure page and Import tab.
-
Click Sheet and select Import.
-
In the Import Spreadsheet dialog box, click Choose File and select the project structure excel created just before.
-
Leave the Format as Excel and select Import Rule for Incoming Records > Create New/ Update Existing.
-
Click OK, and then click Save on the top right corner.