Update schedule - HxGN Smart Build - Version 5.0 U3 (5.0.3) - Help

HxGN Smart Build Insight Help

Language
English
Product
HxGN Smart Build
Subproduct
Insight
Search by Category
Help
  1. Click Schedule Management > Production Planning .

  2. Click Options next to the Preferences , and then select Reschedule.

If the calendar is updated after the last schedule update, then when you click Reschedule:

  • End date and time are calculated based on duration, start date and time, and the updated calendar. If you change the start date of a work package in the production planning timeline by dragging work package container, the application prompts you to add a constraint to ensure the updated start date remains intact. This avoids any unintentional changes to your schedule after rescheduling.

  • Dates of successors are calculated based on predecessors, lags, and calendars.

  • Parent WBS dates are automatically set based on the work package dates, but the duration of the WBS is calculated based on the default project calendar.

  • If the work package start dates are updated in the staging schedule, upon approving it, the application updates all the child work steps dates according to the updated work package start date. To know more, see What happens to the child work steps if I change the work package start date?