Scenario: While reviewing a work package, you notice that the work package is not progressing as expected. Therefore, you want to raise an issue in the Smart Build Insight application. |
-
On the left bar, click Issue Management .
-
On the Issue Management panel, click New Issue .
-
Enter or select the following details:
Category: General
Type: Schedule
Discipline: Architectural
Subject: Delay in the schedule
Description: Delay in the schedule planned for ground floor concrete
Priority: High
Due Date: [Date after week from today]
-
In the Owner tab, click Add.
-
Select the trade manager [Traininguser1] and click Add.
-
In the Assignees tab, click Add.
-
Select the trade manager [Traininguser1] and click Add.
-
In the Work Packages tab, click Add.
-
Select 00_S_Footings F/R/P and click OK.
-
Click Submit.
You can now see the created issue in the list.