What happens to my child work steps if my work package start date is changed? - HxGN Smart Build - Version 5.0 U3 (5.0.3) - Help

HxGN Smart Build Insight Help

Language
English
Product
HxGN Smart Build
Subproduct
Insight
Search by Category
Help

If you do this

The application updates

Change the work package start date

All the child work steps dates according to the work package start date.

Change the work package start date and extend the duration

All the child work steps dates according to the work package start date.

  • In the production planning timeline, the application appends additional duration at the end of the work package container.

  • In the project schedule Gantt view, the application appends additional duration at the end of the work package bar.

Change the work package start date and then reduce the duration

All the child work steps dates according to the work package start date. In the production planning timeline, the work steps that extend beyond updated work package dates are shown as hanging work steps.