See what the upcoming tasks are - HxGN Smart Build - Version 5.0 U3 (5.0.3) - Help

HxGN Smart Build Insight Help

Language
English
Product
HxGN Smart Build
Subproduct
Insight
Search by Category
Help
  1. Click Schedule Management > Smart Visualization Visualization.

  2. At the top-right corner of the animation control bar, under 4D Visualization, choose Planned.

  3. In the View box, choose Look ahead.

  4. Using the Start date and End date boxes, choose the time frame you're interested in.

    The model elements are color-coded by when work is planned to start and end, relative to the dates you picked.

    Color

    Indicates that the work package should

    Before

    Finish before the selected interval

    Before and During

    Finish within the selected interval

    During

    Start and finish within the selected interval

    During and After

    Start within the selected interval

    After

    Start after the selected interval

    Before, During, and After

    Already be in progress, and finish after the selected interval

The legends in Smart Build Insight come with default set of colors and delay ranges. You can change the colors and delay ranges as per your requirements and also choose between single delay or major and minor delays. To customize the legends, go to Administrator Settings > Configure formatting.

What happens when I select a model element in the Model?

If you select a model element, the work package associated with the selected model element is highlighted in the schedule above. This helps you to quickly locate the related work package in the schedule, drill down to see the start and finish dates, and further analyze the progress.