  • The Publish to P6 option is only available when the Primavera P6 EPPM project is integrated with Smart Build Insight.

  • If you have integrated both EcoSys and Primavera P6 EPPM with your project, you must first select an existing EcoSys project and integrate with it before clicking Retrieve from P6 or Publish to P6.

  1. Click Schedule Management > Scheduling .

  2. Click Options > Publish to P6.

    The application publishes the schedule, milestones, and calendar related to the integrated project in P6.