Scenario: You notice that the field construction workers completed 75% of a work step in the 00_S_Footings F/R/P work package. Now, you want to update the progress in Smart Build Insight application as well. |
-
Select [Work Package 1] from the list of work packages.
-
Click the Work Steps tab at the top of the screen to view the list of work steps.
-
Click the work step that you want to progress. For example: Digital Layout of Formwork.
-
Select 75% under completion percentage.
You can see a success message indicating the change is done.
-
Click X icon on the top left of the Overview screen to close the work steps overview screen.
The progress of the entire work package is also changed from 0% to 15%.