On the hamburger menu, click Schedule Management > Production Planning .
-
Enter the following details:
-
Time Range - 2 Weeks
-
View Format - Compact
-
Current view period - February 22, 2021 – March 7, 2021
-
-
Click Edit at the top right corner, and navigate to the Level 4 South Columns work package.
-
On the work package, click Options and select Edit.
-
Change the Planned End Date to March 4, 2022 4:00 PM and then click SAVE.
-
Now, place the cursor on the right border of the Stripping work step and drag it till March 3rd, 2021.
-
Similarly, drag the QA or Acceptance work step till March 4th, 2021.
-
Click SAVE.
-
Hover your mouse on the Stripping work step.
The application displays its details in the tooltip.