Update the work progress by percentage - HxGN Smart Build - 4.0 U10 (4.0.10) - Training

HxGN Smart Build Insight Training

Language
English
Product
HxGN Smart Build
Subproduct
Insight
Search by Category
Training
  1. Log in to the mobile app.

    Notice that the work packages assigned to you are visible under Assigned work package list. Also, in Issues, you can now easily search work packages using their IDs or names, while viewing the issues or adding the work packages to an issue. 

  2. In the Work Packages tab, at the top, select Assigned and then tap the Level 4 South Columns work package.

  3. Tap the Work Steps tab and then tap the Formwork and Prep work step.

  4. Tap UPDATE PROGRESS, and enter 100% and then tap UPDATE.

    Progress of the Formwork and Prep work step and the progress of the Mezzanine Level Columns work package is updated.