You can select sequences within an import schedule to copy to a new import schedule. Then, you can modify the new import schedule for your specific needs. This task is helpful when a sequence within an import schedule has an error and you want to run that sequence again to resolve the issue. The Save Selected As New option is available only if the IntegrityDataCollector2 service is running on the Integrity server or data collector specified in the import schedule you want to copy.

To copy a data import schedule:

  1. In the Admin Utility, click the Schedules link.

  2. Expand the schedule to be copied by clicking the plus sign (+) next to the schedule name.

  3. Check the check box next to each sequence that you want to copy to the new schedule.

  4. Right click on the schedule name, and click Save Selected As New.

The list of schedules is disabled while Integrity creates the new import schedule with the selected sequences. When finished, the new import schedule is added to the Schedules tab and the schedule name is set to Copy_of_originalschedulename. You can then modify the new import schedule as needed. For more information, see Modifying a Data Import Schedule.