You can establish a set of imported data as a baseline. This baseline can then be used to compare against for evaluating imported data. These comparisons can help you identify imported data that may have issues. The Set Import Time as Baseline. button is available only if you have configured data Integrity and the Import Time Change option. For more information, see Data Integrity.

To set an import time as the baseline:

  1. In the Admin Utility, click the History of Imports link.

  2. In the Assets field, select the asset you want to restore to a previous version of imported data. The Import Events list displays the import events for the selected asset.

  3. In the Import Events list, click a row to select that import event.

  4. To set the selected event time as the baseline by which the Import Time Change is compared, click Set Import Time as Baseline. For more information about this baseline and the Number of Changes and Import Time Change options, see Data Integrity.