Open the required project.
-
Add the items that you require. For details, see Add Items to the Project Management Table in a Project.
-
Select the check box beside each item that you want to mark as completed. For details of item statuses in the project, see Rules for Changing Statuses.
-
Do one of the following:
-
Click on the Project Management toolbar.
-
Right-click in the Project Management table and then on the shortcut menu, click Mark as Completed.
-
-
Click the Apply command to claim the items.
The items that have been marked as completed are no longer available for editing in the project and are ready for merging into the As-Built.