Automatically add items to a WBS item as I create them - Intergraph Smart 3D - Help

Intergraph Smart 3D Common

Language
English
Product
Intergraph Smart 3D
Subproduct
Common
Search by Category
Help
Smart 3D Version
13
  1. Select More from the WBS list to display the Select Active Project Dialog.

  2. Select the active WBS Item, and click OK.

  3. Create objects in the model.

    As objects are created, the software automatically assigns them to the active WBS project and WBS Item.

  • If a WBS project is chosen as the Active WBS, then all objects you create are automatically assigned to that project. The access control rules that control manual assignment apply for the automatic assignment.

  • If a WBS Item is chosen as the Active WBS, then only specific object types are automatically claimed to the parent project of the WBS Item and then assigned to the WBS Item. Only the lowest-level objects that are included in deliverables and have identity are automatically assigned. In other words, design objects, such as piping features, or grouping objects, such as pipelines, are not automatically assigned, but piping parts are assigned. You must manually claim any system object to a Project and manually assign it to a WBS Item.