  1. From within a Smart 3D design session, click Project > Re-Synchronize Command to open the Re-synchronize dialog.

  2. Select a project in the list.

  3. Select Error Objects or All Objects to specify the objects that display in the Data Grid.

  4. Select the design objects that need to be marked for synchronization to SDx2.

  5. Click Re-synchronize to process the selected objects.

  6. Click Yes in the confirmation box.

    When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx2 by the Share Service.

  7. Click OK to close the message box.

  8. Click Close to close the Re-synchronize dialog.

Smart 3D Standard model

  1. From within a Smart 3D design session, click Project > Re-Synchronize Command to open the Re-synchronize dialog. The software populates the Data Grid with data error objects, if any exist.

  2. Select the error objects that need to be marked for synchronization to SDx.

  3. Click Re-synchronize to process the selected objects.

  4. Click Yes in the confirmation box.

    When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx2 by the Share Service.

  5. Click OK to close the message box.

  6. Click Close to close the Re-synchronize dialog.

You can also mark design objects to be resynchronized to SDx2 with the the SDx Synchronization Status Monitor or in Project Management. See Re-synchronize objects to SDx2 in the Project Management Help.