Recover from Satellite failure - Intergraph Smart 3D - Administration & Configuration - Hexagon PPM

Intergraph Smart 3D Global Workshare (Oracle)

Language
English
Product
Intergraph Smart 3D
Subproduct
Global Workshare
Search by Category
Administration & Configuration
Smart 3D Version
13

The following workflow explains a procedure for recovering the Satellite server in a Global Workshare Configuration (GWC) environment in the event of a failure. A Satellite server can fail due to hardware or other catastrophic failure. This workflow allows the GWC to remain active; only the lost Satellite location experiences an immediate work stoppage.

The overall workflow consists of removing the failed satellite, performing cleanup actions, and adding the new satellite server.

  1. Using the Host administrative client, open the Project Management task, and run Consolidate Model from Workshare for the failed satellite location. See Consolidate Oracle databases.

  2. Copy the scripts generated onto the corresponding servers. See Copy generated scripts into GoldenGate folders. Because the Satellite server being repaired might be unavailable, you only need to copy the consolidation scripts onto the Host server's GoldenGate folder.

  3. Run the consolidation scripts on the Host and all corresponding Satellite servers.

  4. If the Satellite server is online, delete all Smart 3D databases that were previously participating in replication.