Synchronizing the work area definition from the As-Built model in SDx provides a reference for the Smart 3D project assigned to the external EPC.
-
We recommend stopping the Share service on the As-Built (Handover) model before synchronizing the work area to the Change Management model. When data merged to SDx in a Change Management workflow is reworked in the As-Built (Handover) model when the Share Service is running, overlapping objects in the work area can occur and lead to downstream integrity issues.
-
Before synchronizing the work area definition, you must define SDx subscription settings. Otherwise, the software displays an error message.
-
Open Project Management, and select the registered Change Management model in the Project Management tree.
-
Click Integration > Synchronize Work Area from SDx Command to open the SDx Synchronization Status window.
-
Review the progress for the synchronize from SDx process. The Sync from SDx progress bar displays 100% when the work area definition is synchronized (1), and Sync Status in the Synchronize from SDx panel displays Completed (2).
-
Click Close when finished.
-
If an instance of work area definition synchronization is currently in progress, the software displays a message.
-
After you synchronize the work area definition, you can claim the objects to be modified.