The following reports are delivered in Smart Construction. Some reports may be delivered, but not enabled.
Each Smart Construction report is delivered as an individual load file, located in the 090-Reports folder in the installation location (for example, browse to [Drive]\Program Files\SmartConstruction\LoadFiles\Current\003-Admin\090-Reports). You can load each report individually, or you can select all reports to load.
Report Name |
Enabled by Default? |
Scope |
Description |
---|---|---|---|
CWP Schedule Breakdown |
Yes |
Project wide |
Displays all IWPs and their dates planned for a CWP. The report also displays all dates related to a CWP |
CWP Summary |
Yes |
Individual CWPs |
Displays a summary of a CWP, including a forecasted, planned, and completed man hours. |
Planned vs. Actual Man Hours |
Yes |
Project wide |
Displays IWP actual and planned man hours grouped by discipline and purpose. |
Progress Summary by CWP |
Yes |
Project wide |
Displays the progress of your construction project, broken down by contractor and CWP. You can use selection criteria on the Report Options dialog box to filter and display specific information. |
Progress Summary by IWP |
Yes |
Project wide |
Displays the progress of your construction project, broken down by contractor, CWP, and IWP. You can use selection criteria on the Report Options dialog box to filter and display specific information. |
Scorecard |
Yes |
Individual IWPs |
Displays the components associated with an IWP. Best viewed as an 11" X 17" document. |
IWP Summary |
Yes |
Individual IWPs |
Displays the contents of an IWP. Best viewed as an 11" X 17" document. |
IWP Summary Brief |
No |
Individual IWPs |
Displays the contents of an IWP, excluding attached files and drawings. Best viewed as an 11" X 17" document. |
IWP Progress Details |
No |
Individual IWPs |
Displays progress for individual components in an IWP. |
Work Scope by Discipline |
No |
Project wide |
Displays the progress of the work scope, broken down by discipline. The progress of each discipline is listed as a percentage of the total work scope. |