Click Work Packages on the project home page.
-
Select an IWP from the Work Packages browser.
-
Click Components.
-
Click Refresh Work Steps.
-
Select Add New and Unassigned Work Steps to IWP to add any new and unassigned work steps to the IWP.
-
Select Refresh Work Steps Only to refresh the work step data.
The following table describes what happens with work step data when it is refreshed:
Add a new work step |
Update an existing work step |
Remove a work step |
|
Work step that is in an IWP, and it does not have any progress reported |
The new work step is added to the system, but it is not associated to any IWP. |
The work steps are updated. |
The work step is converted to a manually added work step. |
Work step that is in an IWP and has progress reported |
The new work step is added to the system, but it is not associated to any IWP. |
The work step is not updated. |
The work step is not updated. |
-
When you filter data on the Components window column headings and refresh work steps, the action applies to all components in an IWP, not just the filtered portion.
-
When you refresh work steps from the Smart Construction client, those items are given priority in the retrieve queue and are processed before any other items in the retrieve queue.