You can create relationships between IWPs on the Work Package Schedule window. Relationships determine the order in which IWPs are to be planned and completed. These relationships are included on the Work Package Summary report.

You can create the following types of relationships on the Work Package Schedule window:

Relationship name

Type of relationship

How to create the relationship

Finish-to-Finish

The Planned Finish date of one IWP determines the Planned Finish date of another IWP.

Drag the relationship from the right side of the predecessor IWP to the right side of the successor IWP.

Finish-to-Start

The Planned Finish date of one IWP determines the Planned Start of another IWP.

Drag the relationship from the right side of the predecessor IWP to the left side of the successor IWP.

Start-to-Finish

The Planned Start date of one IWP determines the Planned Finish date of another IWP.

Drag the relationship from the left side of the predecessor IWP to the right side of the successor IWP.

Start-to-Start

The Planned Start date of one IWP determines the Planned Start date of another IWP.

Drag the relationship from the left side of the predecessor IWP to the left side of the successor IWP.

For more information, see Create relationships between IWPs on the Work Package Schedule window.