  1. In Smart Electrical, open the host plant (As-Built) and select the project that you want to specify as the host project.

    SPEL Offsite Scope Items 04

  2. Scope the required items to the host project.

    SPEL Offsite Scope Items 05

  3. Open the project and select the plant group where your data resides.

    SPEL Offsite Host Data Export Package 02

  4. Claim the items to the project.

    SPEL Offsite Host Data Export Package 03

  5. Close Smart Electrical.

  6. Open Smart Engineering Manager and connect to the host.

  7. Select the host project and on the shortcut menu, click Save Project as Offsite.

    SPEL Offsite Host Data Export Package 04

  8. On the Save Project as Offsite dialog box, accept the default location for exporting the plant to, or change the location by clicking the Browse button .

    SPEL Offsite Host Data Export Package 05

  9. Click OK to export the host project data as a package. The status bar at the bottom of the dialog box shows the current activity.

    SPEL Offsite Host Data Export Package 06

  10. In Smart Engineering Manager, connect to the off-site plant.

  11. Click Plant Structures and on the shortcut menu, click Load Offsite Plant Structure.

    SPEL Import to Satellite 01

  12. On the following page of the Load Offsite Plant Structure Wizard, beside Zip file of plant, click the Browse button .

    SPEL Load Offsite Plant Structure DB 00

  13. Browse to the zip file containing the package from the host that you want to load.

    SPEL Import to Satellite 02

  14. Click Next. The page shows you details of the package.

    SPEL Load Offsite Plant Structure DB 01

  15. In the Name field, type the name of the new plant to be created in the off-site plant.

    SPEL Load Offsite Plant Structure DB 03

  16. To create a project in the plant, select the Project check box.

    SPEL Load Offsite Plant Structure DB 04

  17. Specify the plant structure path (in this example, the plant structure path was copied from the folder path one level above the backup location).

    SPEL Load Offsite Plant Structure DB 06

  18. In the System user and System password fields, type appropriate values for your database.

    SPEL Load Offsite Plant Structure DB 07

  19. Click Next to accept the database server and user connection information or specify a different path for the Smart Electrical reference data.

    SPEL Load Offsite Plant Structure DB 08

  20. Click Finish to load the package and create the new As-Built and project for the off-site plant.

    SPEL Load Offsite Plant Structure DB 09