Synchronize Plant Operating Cases - Intergraph Smart Electrical - Help - Hexagon

Intergraph Smart Electrical Help

Language
English
Product
Intergraph Smart Electrical
Search by Category
Help
Smart Electrical Version
10

The software checks for plant operating case inconsistencies when selecting a project in the As-Built or opening a project in Project Management.

If the software detects a case inconsistency between the As-Built and the selected project, you have to synchronize the plant operating cases that have been found as inconsistent. The names of these cases are shown by the software in the warning message that opens automatically once an inconsistency is detected. Inconsistencies can occur when adding, deleting, or renaming plant operating cases in the As-Built or one of the existing projects belonging to the As-Built. For example, if you add a plant operating case in a project, you will have to add the same case in the As-Built in order to merge the case data into the As-Built.

Synchronize Plant Operating Cases

  1. In Options Manager, select Tools > Manage Plant Operating Cases.

  2. On the Manage Plant Operating Cases dialog, add, delete, or rename the plant operating cases that have been detected as inconsistent.

  3. In Smart Electrical, open Project Management and select the project that had inconsistent cases.

  4. If no warning message appears, all the cases have been synchronized.