The following workflow demonstrates how to compare drawings in a connected Workshare collaboration using projects.

1

Project 1 checks out Drawing A.

Project 1 assigns ownership of Drawing A to Satellite 1.1.

2

Project 2 fetches Drawing A from Project 1.

3

Project 2 assigns ownership of Drawing A to Satellite 2.1.

4

Satellite 2.1 opens, claims items, and modifies Drawing A.

Drawing A becomes Drawing A'.

Satellite 2.1 exits Drawing A'.

5

Satellite 2.1 assigns ownership of Drawing A' to Project 2.

6

Satellite 1.1 opens, claims items, and modifies Drawing A.

Drawing A becomes Drawing A''.

Satellite 1.1 releases claims and exits Drawing A''.

7

Satellite 1.1 assigns ownership of Drawing A'' to Project 1.

8

Project 1 checks Drawing A'' into the Plant.

9

Project 2 checks out Drawing A'' (without replacing Drawing A').

10

Project 2 compares Drawing A'' (modified in Project 1) with its own Drawing A'.

11

Project 2 refreshes Drawing A' with differences from Drawing A''.

Drawing A' becomes Drawing A'''.

12

Project 2 checks Drawing A''' in to the Plant.