Displays the New Project dialog, allowing you to create a project within the Plant. You must enable the plant for projects before you can access this command.

  • Project names must be unique within the plant and cannot contain any of the following characters: ~ ` ^ & - + , . ? |

  • You do not have to be a site administrator to create a project, however if you create a project without site administrator privileges, you will have no privileges in the project. Users without site administrator privileges can create a project and add a role as long as they do not exit Smart Engineering Manager. If they exit the program without adding themselves to a role with necessary privileges, they will not be able to add roles or create plant groups in the project.

  • Before creating the project, be sure to set the claim mode using the Settings view in Smart P&ID Options Manager (see Understanding Reference Data Settings in the Smart P&ID Options Manager Help). The claim mode is either Exclusive (default) or Shared, and applies to the Plant and all its projects. If you plan to use the project in an integrated environment, Exclusive mode is mandatory.

  • You can change the claim mode to Shared at any time. However, you can change the mode to Exclusive only when there are no claims in any project in the Plant.