This project default is used for advanced approval.
It is used on R.30.01 to determine how many steps must be performed when approving and releasing an engineering requisition.
If the project default is set to N (default value), there is no logic behind the RfA check box (Ready for Approval). A button with the label Release appears. When you click this button, the engineering requisition is not only approved but at the same time released to procurement.
If the project default is set to Y, there will be a button labeled Approve on R.30.01. This button is only enabled if the RfA check box has been checked. When you click the button, the engineering requisition is approved. At the same time the label of the button changes to Release. For finally releasing the requisition to procurement (in a later step), you must click this button again, now labeled Release.
-
Module(s) affected by this setting: A2049, R3001
-
Default value: N
-
List of Values: N/Y