With this project default you define if negative other costs are allowed.
When entering cost values for other costs, this project default is needed. If it is set to N (default), you can only enter values >= 0 in screen D.50.12 Attached Other Costs. If ZP_NEG_OC is set to Y, you may also enter negative values.
-
Module(s) affected by this setting: D5012, P3021, P3022, P3026, P3027, P5007, OPI1001, Smart Materials Portal
-
Default value: N
-
Available values: N/Y