Take requisition quantity.

With this project default, you control the quoted quantity on inquiry supplements and updated inquiries.

If the project default is set to N (default), the quantity newly released to procurement by engineering is added to the current quoted quantity.

If the project default is set to Y, quantities changed by the bidder or the buyer are ignored. Only the released quantity is taken into account.

Example:

With requisition supplement 0, a quantity of 10 has been released; with requisition supplement 1, a quantity of 20 (which means a delta of +10).

For requisition supplement 0, an inquiry has been created. The bidder (or the buyer) has increased the quoted quantity from 10 to 15.

If ZP_REQ_QTY has been set to N, the quoted quantity of the inquiry supplement created for requisition supplement 1 will be 25 (= 15 (previously quoted quantity) + 10 (delta quantity coming from requisition supplement 1)).

If the project default has been set to Y, the quoted quantity of the inquiry supplement will be 20 (= 10 (originally quoted quantity) + 10 (delta quantity coming from requisition supplement 1)).

Please note that this project default is not taken into account when creating a manual inquiry supplement (not driven by a requisition supplement) by clicking New Supplement in screen P.30.11 Inquiries.

  • Module(s) affected by this setting: P3001, P3003, P3021

  • Default value: N