Summarize other costs in display in screen P.50.07?
This project default is used to determine how other costs are to be displayed in screen P.50.07 Maintain Agreements.
If the project default is set to N (default), one record is displayed for each supplement where an other cost was included.
If the project default is set to Y, the total for each other cost over all supplements up to the current supplement is shown.
Example:
ZP_SUM_OC = N
OC-1 0 10 EUR
OC-1 1 5 EUR
OC-1 2 20 EUR
OC-2 0 10 EUR
OC-2 2 20 EUR
ZP_SUM_OC = Y
OC-1 2 35 EUR
OC-2 2 30 EUR
Please note that project default ZP_SUM_OC only influences the display of data. It has no influence on the way the data is stored in the database.
-
Module(s) affected by this setting: P5007
-
Default value: N
-
List of Values: N/Y