ZC_UPD_EXP - Intergraph Smart Materials - Version 10.2 - Administration & Configuration - Hexagon

Intergraph Smart Materials Classic Administration (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Administration & Configuration
Smart Materials/Smart Reference Data Version
10.2

This project default specifies whether to update the actual on site date in expediting for all item shipments that are included in the material receiving report (MRR) with either the receiving date of the item shipment or the system date when the MRR is posted.

Set this project default to Y if you want to update the actual on site date with the receiving date of the item shipment.

Otherwise, if ZC_UPD_EXP is set to N (default), the actual on site date in expediting is filled with the system date.

If you are working with the extended expediting module (ZP_NEW_EXP set to Y), the actual date of the destination which is of date type Arrival On Site is set correspondingly.

  • Module(s) affected by this setting: C2001, C200102, C2004, C2005, C2007

  • Default value: N

  • List of Values: N/Y