SOW Milestones - Intergraph Smart Materials - Version 10.2 - Help - Hexagon

Intergraph Smart Materials Classic Help

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

On this tab, you can attach SOW milestones.

This tab is only available for subcontracting inquiries or requisitions.

You can select the date of the start activity from the LOV in the Start Work field.

Select the name (code) of the start activity from the LOV in the Start Activity field. Activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the substantial activity from the LOV in the Substantial Completion field.

Select the name (code) of the substantial activity from the LOV in the Substantial Activity field. Substantial activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the final activity from the LOV in the Final Completion field.

Select the name (code) of the final activity from the LOV in the Final Activity field. Final activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

In the Interim Milestones block, you can maintain SOW milestone details (interim milestones) attached to requisitions.

The Seq field displays the order sequence of the interim milestone.

The description of the interim milestone is shown in the Interim Milestone field.

Select the name (code) of the activity assigned to the interim milestone from the LOV in the Activity Code field. Activities are maintained on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the activity from the LOV in the Date field.