To update the transit days of a routing method, proceed as follows:
-
In the Master Data navigation panel, select Procurement > Routing Methods.
-
Select a Delivery Designation, click the Routing Methods tab, and select a Routing Method.
-
In the grid on the right, type the Transit Days and click Save.
-
If the routing method is assigned to release notes, do the following:
-
In the opened dialog, select the release notes that should be updated according to the changed transit days.
-
Click Reconcile.
If you close the dialog and acknowledge the message by clicking Yes, forecasted dates on release notes are not updated.
-