Recalculate planned dates - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
(WPF)
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2
  1. Enter a planned date for one milestone.

    • If you enter more than one planned date, the recalculation will consider only the value of the milestone with the lowest sequence. All other values will be overwritten.

    • For a two-phase planning, you must enter a date in the 1st phase (between first milestone and 1st pass milestone) and a date in the 2nd phase (between 2nd pass milestone and the last milestone).

  2. If the plan has changed from the original plan, update the values in the Days cell accordingly.

  3. Click Save.

  4. Click Select an Option WPFSelectOptionIcon.

  5. Click Recalculate Planned Dates.

    The planned dates are calculated based on the entered date(s) + span days + add days.

SHARED Tip To delete the planned dates, click Select an Option WPFSelectOptionIcon > Clear Planned Dates.