If the plan has changed from the original plan, update the values in the Days cell accordingly.
-
Click Save.
-
Click Select an Option .
-
Click Recalculate Forecasted Dates.
The forecasted dates are calculated based on the entered date(s) + span days + add days.
-
Locked forecasted dates will not be overwritten.
-
If a forecasted date is later than the corresponding planned date, the delay appears in the Days Late cell.
-
To delete the forecasted dates, click Select an Option > Clear Forecasted Dates.