Assign planned tags to planned requisitions - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
(WPF)
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2
  1. Click the Planning task on the dashboard, or select Planning from the Tasks list.

  2. Select a planned tag in the tree.

    The planning item details appear on the right panel.

  3. Click Planning to display the Planning section.

  4. Select the Planned Requisitions tab.

  5. Click Add Engineering Requisition Com_Add ICON.

  6. Select the check box in the first column for all requisitions you want to assign to the selected planned tag.

  7. Click Add.

  8. Click Save.

SHARED Tip To remove a requisition, select the record and click Delete ICON Remove.

The Agreement Number column is only displayed if project default ZP_MS_DUP is set to Y. If a planned requisition is linked to an agreement, the corresponding agreement number will be displayed here.