All reports created by the Smart 3D/nesting system are created in XLS format, currently. For Phase 2, it is planned to modify the reports so that they directly created in CSV format. Because process 51 Import MTO data only functions with CSV, all reports must be loaded into Microsoft Excel and must be saved manually into the CSV format.

For better manual check reasons, the reports contain header lines. Those lines must be manually deleted before saving the report as CSV. Also, this manual activity is planned to be eliminated with Phase 2.