Work flow to set up Project Defaults - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Web Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
Web
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

This section explains the specific tasks required to set up the project defaults in Smart Materials Web. You can access and manage project defaults on the Administration > Global Setup > Project Defaults page.

The project default page has the following three tabs:

  • Project Defaults

  • Project Discipline Defaults

  • Project Group Defaults.

Project Defaults 1

  • The project defaults can be set at these levels from top to down; Project Group > Project > Project/Discipline.

  • When a project default has a value of ./., that means the value is not set. In this case, the application uses the hard-coded default value for this setting.

  • The default setting is selected by a module/procedure on the discipline level first, then on the project level, and finally on the project group level. If it is not defined anywhere, an error message occurs.

  • Higher levels only serve as a template for lower levels. This means that if you change a setting at a higher level, then it is effective only if it is not defined at the lower level. For example, if you change a setting at the project level, the discipline setting will still be valid as it was set.

To facilitate a new project set up, project defaults can be copied from other projects or from template projects in different ways.

  • Using the Copy Values button on the Global Setup > Project Defaults page.

  • Using the Copy Admin Setup page, with the Project Defaults or Project Discip. Def. options.

  • Using the Project Setup Copy page, with the Global Setup > Project Defaults function assigned to the Copy Setup.