This project default specifies the origin or department that is responsible for or dedicated to the project. Origins can be defined and maintained on the Global Setup > Materials Setup > Origins page. The Material Take Off (MTO) needs this information to assign an origin to engineering requisitions.

In addition, this project default is used as the default on the following pages: Agreements, Tagged Items PlanningRequisitions PlanningBudget Results, and Requisitions > Maintain Requisitions. This default can be overwritten.

  • Module(s) affected by this setting: Requisition Workload, Procurement > Agreements, Expediting, and Price Breakdown.

  • Default value: ./.

  • List of Values: Global Setup > Materials Setup > Origins.