This project default specifies the ceiling of the estimated value for Blanket Orders (BO) and Master Agreements (MA). The ceiling value represents a percentage applied to the estimated value and is used to check whether the allowed value for a BO or a MA has been exceeded.
For example:
The BO/MA has an estimated value of 100 USD. A first agreement is created against this BO/MA with total costs of 30 USD. A second agreement is created against this BO/MA with total costs of 65 USD. This makes a total of 95 USD. If the project default has been set to 90%, a message appears notifying the exceeding value.
-
Module(s) affected by this setting: Inquiry > Requisition Workload.
-
List of Values: ./.